Bento Fit Out
Early stages of the fit out

6th WeekSixth Week
First floor Bar Area
Wall painted
Side lights in place
Bar Bulk Head
Bar equipment
Storage area for bar is designed
Lights fixtures in place
Column has been made into a feature using
Armour Coat plaster effect
First floor bar area
Toilets tiling and toilet bowls are in placed
1st Images
Before Images
Week One
The downstairs area of the premises after removing
ceiling. All services were shut down and secured.

3rd Week
Third Week
Kitchen counter in ground floor has been bricked up
Walls have been plastered
Disabled toilet is in placed and plaster boarded
Opening in first floor has been rendered
Wall partition has been put up for new toilet area
Ceiling frame has been put up in first floor has
been put up.
Air conditioning brackets are now in place
Front Hoarding in place while shop front is being
built.
Health and Safety Requirements
4th Week
Fourth Week
Kitchen Canopy in place in the ground floor
Stainless Steel sheeting on the walls are also up
Air Conditioning Unit in plaster
Electric box access
First floor bar area, walls plastered and ceiling
plaster boards.
Old toilets removed and rearranged, wall rendered
5th WeekFifth Week
First floor Bar area
Python in place
Ceiling painted
Toilet entrance now in place
Wall completely rendered
Basement area where beer barrels are stored
Python leads up from basement to ground floor
and first floor
Ground floor
Kitchen floor being placed
2nd WeekWeek Two
First Floor Proposed Bar Area
The Load Bearing wall supported
by an Acrow Jack's prior to breaching
the wall for better flow between the 2 bar
sections. Lintel supporting the wall
View into the 2 section of the proposed bar
area.
7th Week
Seven Week
Ground Floor
Kitchen area counter front has been rendered
Partition suspended from ceiling to obscure view
into the toilet area
First Floor Bar Area
Digital wall paper in place
Wall painted
Back of Bar
Fridges in place
Python in place
First Floor Bar Area
View from gap of partition into lounge seating
area.
8th Week
Week Eight
Finished work and only require finishing touches
Reception desk in place
Shop front completed and as you can see entrance
has been moved from right to left ( that applies
if you are standing outside the restaurant
facing the front of the restaurant
View tin to open kitchen
Disabled toilet completed
First Floor bar area